Soil Investigation

  • Field and laboratory investigation is required to obtain the necessary data of the soils for the successful construction of any structure at the site are collectively called soil exploration or Sub surface Investigation .
  • The choice of the foundation and its depth, the bearing capacity, settlement analysis depend very much on the engineering properties of the soil .

The primary objectives of soil exploration are

  • To assess the general suitability of site
  • To Find the Bearing Capacity of the soil
  • To select type and foundation for a given structure
  • To Investigate the nature and depth of each stratum and assess required properties.  
  • To Predict possible difficulties and problems in site  and suggest remedial actions  
  • To Select a suitable construction materials in site and suggest remedial actions 
  • To Study shrinkage and swelling potential 
  • To Study ground water conditions .
  • To determine the depth and nature of bed rock
  • To determine the water table and its fluctuation

Methods of exploration can be broadly classified into two categories:

 

Direct Method

Boring or trial pits at a predetermined location to the required depth and fairly intact samples of soils from every stratum encountered or at suitably selected depths is obtained which are utilised to get necessary information about the soil characteristics.

Exploration by Test pits

Pits are dug manually but mechanical equipment may also be used for the purpose up to shallow depths. In dry ground, pits are economical in comparison to bore holes up to a depth of about 5m depending upon the location. As the depth increases, the cost of excavating a pit increases very rapidly and it is seldom that unsupported pits are dug to a depth exceeding 6 m except in the case of hard soils. The top of a pit shall be kept large enough so that dimension of the pit at the bottom may be at least 1.2 m X 1.2 m which are sufficient to provide necessary working space. Additional space for sheeting and timber support, hoisting arrangements and ladder, etc. shall be provided.

Exploration by Test pits

For deep pits in soil, the walls shall be supported by timber. During excavation, the pit should be kept fairly level and of full section so that each lift may represent the corresponding portion of the deposit in quality and quantity. The excavated material should be placed round the pits as stockpiles, separated when significantly different materials are encountered; and marked stakes should be driven in to the stockpiles to indicate the depth from which the materials were excavated in order to facilitate logging and sampling latter on. The excavated material should be placed round the pits in the manner it is received from the excavation, preferably in a clockwise direction. The deposits of excavated material from the pit at every change in strata should be dumped separately in the manner described above. Samples from these deposits should be taken as soon as material comes out of the pots and the natural water content of the excavation material determined. Test pits left open for inspection shall be provided with covers or barricades for safety. Pits and trenches shall be suitably fenced. Trenches and pits should be filled back properly.

Exploration by Trenches

Test trenches are useful when a continuous exposure along a given line or section is desired. In general they serve the same purpose as the pit but have the added advantage of disclosing the continuity or limits of the formations or deposits in question and any vertical faults in the rock structured. The field work consists of excavating an open trench from the top to the bottom of the slope to reach representative undisturbed material. Either a single slot trench down the face of the slope or a series of short trenches spaced at appropriate intervals along the slope may be excavated. Depending on the extent of the investigation required, use may be made of picks and shovels; bulldozers, ditching machines, back hoes or dragline. 

Exploration by Trenches

 

Exploration by Borings:-

When the depth of exploration is larger borings are used for exploration .

Methods of Borings (As per IS 1892:1979)

Auger boring- these are suitable for advancing holes up to a depth of 3 to 6m in soft soils

Exploration by Borings

Wash boring- Used for advancing hole in the ground. This method is slow in stiff soils and coarse grained soils.

Rotary drilling- Can be used in clay sand and rocks.

Percussion drilling- used for drilling holes in rocks boulders and other hard strata

Core drilling- used for drilling holes in rock and for obtaining rock cores( for identification and tests)

Exploration by Borings and Drilling

Hand Auger Borings - Auger boring is the most common, economical and rapid method for relatively shallow exploration of fine - grained materials above the water - table. Hand augers become awkward and cumbersome beyond a depth of approximately 6 m. If the work is done carefully, the layers of different soils may be accurately located, identified classified and suitable distributed samples obtained.

Exploration by Borings and Drilling

 

Power Auger Borings - The most suitable type of power-auger for soil investigations is the one that will drill a hole at least 60 cm. in diameter (preferably 70 cm to 90 cm), which is large enough for a man to enter and make accurate inspection or sampling of the soil in place. These large-size augers will drill into slightly cohesive soils containing appreciable quantities of gravel up to 7.5 or 10 cm in size. Power-augers are not satisfactory for use in bouldery materials.

Power Auger Borings

Most augers permit boring of holes of about 2.5 m to 3.65 m depth. However, more recent equipment allow boring up to 6 m or even 12 m depths.

Power Auger Borings

This type of exploration has to be resorted where the required strata or deposit in case of investigation of materials, cannot be reached by the methods mentioned above or where the compaction or the soil strata or presence of boulders and rock make it necessary. 

 

Power Auger Borings

 

Indirect Methods

These methods include various sounding and geophysical methods, indirectly by measuring in-situ a tool/instrument behavior during interaction with soil/rock and inference of material properties. eg. SPT, cone penetrometer  etc.
Choice of method depends on budget, sampling requirements, extent of investigation, and often site conditions.

VANE SHEAR TEST

Vane shear test (VST)- to determine shear strength of cohesive soil in its natural condition.( Is 4434:- 1978)The vane shear test is most appropriate for the determination of the shear strength of saturated clays, especially of the ‘soft’ to ‘medium’ consistency. 

The test is especially appropriate for determining the shear strength of sensitive soils which are highly susceptible to sampling disturbances.

VANE SHEAR TEST

VANE SHEAR TEST

The vane shear test consists of pushing a four-bladed vane in the soil and rotating it till a cylindrical surface in the soil fails by shear. The torque required to cause this failure is measured and this torque is converted to a unit shearing resistance of the cylindrical surface

 

Standard Penetration Test (SPT)- to determine N-value (IS 2131-1981)

IS 2131 :1981 (Reaffirmed 1987):  Indian standard – Method for standard Penetration test for soils .SPT is widely used to determine the parameters of the soil in situ .

The test consists of driving a split spoon into the soil through a borehole at the desired 

depth . This test was developed in 1920 Consist of 3 parts 

 

-Driving shoe at bottom- 75mm long 

-Steel tube, split longitudinally into 2 halves-450mm long 

-Coupling at the top-150mm long .

SPT

SPT

SPT

The split spoon sampler is driven into the soil a distance of 450 mm at the bottom of the boring 

A hammer of 63.5 kg wt with a free fall of 760 mm is used to drive the sampler .

The no. of blows for a penetration of last 300 mm is designated as the “ Standard Penetration Value” or “Number” N

SPT

 

 

Standard Penetration Test

 

Cone Penetration Test (CPT)- to determine type of soil using electronic measuring system that records tip resistance and friction

SPT

 

PLATE LOAD TEST (IS 1888:1982)

Plate bearing test is an important field test for determining the bearing capacity of the
foundation. In this test a compressive stress is applied to the soil pavement layer through  rigid plates of relatively large size and the deflections are measured for various stress values.

 

PLATE LOAD TEST

 

 

 

Spacing of Bore Holes

Structure 

Minimum No of Bore Holes 

Check dams 

At abutment points and at 20 m intervals in 

river course (minimum one number in river course).

Regulators

Borehole should be taken at all pier points and 

abutments. (Usually the centre to centre distance 

between the pier is standardized to 14m

Side protection Works 

If these works are necessary, bore holes should be taken on the banks at the upstream and downstream of the structure at 

30 m intervals along the required length.

Cut off walls.

At positions of cut off walls , for designing Apron.

 

 

 

If the Site Engineer in charge feels that there is a necessity of closer bore holes then he should execute as per site conditions

 

Development

Test Spacing

Approximate Depth of Investigation

Dams

25 m to 50 m

2 x height of dam, 5 m below toe or of slope. 3 m into bedrock below toe whichever is greater. Extend into zone of low permeability.

Canals

100 m to 200 m

3 m minimum below invert level or to a zone of low permeability

Culverts 

<20 m width

20 – 40 m

1 Bore hole One at each end

One at each end and 1 at 

middle with maximum spacing of

 20 m between bore holes

2 B – 4B but below base of compressible layer

 

SUB SOIL EXPLORATION REPORT

 

The following details should be attached to the report:

 

1. Latitude and longitude of location

2. Site location map

3. A plan view of the location of the borings with distance between them with respect to the proposed structure

4. Boring logs

5. Laboratory test results

6. SBC and N value of each layer 

7. For rocky strata, the RQD value should also be included

8. For rocky strata, the RQD value should also be included

9. Report should be authenticated by field officers.

 

BENCHMARK

LOCATION AND NUMBER OF B.M

 

S.

No.

Particulars

Standard/

permanent B.M

Location &No.

Ordinary or Temporary B.M.

Location & No.

1.

Major Dam &

Medium

One on either bank along the alignment

Dam alignment excluding river

portion @10 chains located D/s at

a distant of five times the head of

the dam away from the C/L of the

dam.

One on Waste weir at a distance of

2 chains from the mid pointed of the

C/L of the alignment.

Spill channel & approach channel

alignment one @ every 10 chains.

2.

Minor Dam

One on one bank

Same as for Sl. No. 1above

3

Canal alignment

At every 5 km 

along the 

alignment, on the canal boundary line

At every one km along the

 alignment, on the boundary line 

excluding standard B.M.S.

 

PLATE LOAD TEST

IS 2131-1981

Method for standard Penetration test for Soils

 

IS 7720-1991

Criteria for investigation planning and layout for barrages and weirs

 

IS 1892-1979

Code of Practice for subsurface investigation for foundations

 

IS 11385-2008

Sub surface exploration for canals and cross drainage works

 

IS 4453 :2009 

Code of practice for subsoil exploration by pits trenches etc

 

Is 4434:- 1978

Vane shear test (VST)- to determine shear strength of cohesive soil in its natural condition.  

 

 

IS 6955-1973

Bore Hole spacing guidelines for Earth and rock fill dams 

 

 

IS 11385,1985

Bore Hole spacing guidelines for canals and cross drainage works

 

IS 2720 

(Part 2)1973

Determination of water content (second revision)

 

IS 2720 

(Part 5)1985

Determination of liquid and plastic limit (second revision

 

IS 6403-1981

Code of practice for determination of bearing capacity of shallow foundations.

 

IS 1498:1970

Classification and identification of soils for general engineering purposes (first revision

 

IS 2720 

(Part 1)1983

Preparation of dry soil samples for various tests (second revision)

 

 

 

 

INVESTIGATION-IS CODES