Methods of exploration can be broadly classified into two categories:

Direct Method

Boring or trial pits at a predetermined location to the required depth and fairly intact samples of soils from every stratum encountered or at suitably selected depths is obtained which are utilised to get necessary information about the soil characteristics.

Exploration by Test pits

Pits are dug manually but mechanical equipment may also be used for the purpose up to shallow depths. In dry ground, pits are economical in comparison to bore holes up to a depth of about 5m depending upon the location. As the depth increases, the cost of excavating a pit increases very rapidly and it is seldom that unsupported pits are dug to a depth exceeding 6 m except in the case of hard soils. The top of a pit shall be kept large enough so that dimension of the pit at the bottom may be at least 1.2 m X 1.2 m which are sufficient to provide necessary working space. Additional space for sheeting and timber support, hoisting arrangements and ladder, etc. shall be provided.

For deep pits in soil, the walls shall be supported by timber. During excavation, the pit should be kept fairly level and of full section so that each lift may represent the corresponding portion of the deposit in quality and quantity. The excavated material should be placed round the pits as stockpiles, separated when significantly different materials are encountered; and marked stakes should be driven in to the stockpiles to indicate the depth from which the materials were excavated in order to facilitate logging and sampling latter on. The excavated material should be placed round the pits in the manner it is received from the excavation, preferably in a clockwise direction. The deposits of excavated material from the pit at every change in strata should be dumped separately in the manner described above. Samples from these deposits should be taken as soon as material comes out of the pots and the natural water content of the excavation material determined. Test pits left open for inspection shall be provided with covers or barricades for safety. Pits and trenches shall be suitably fenced. Trenches and pits should be filled back properly.

Exploration by Trenches

Test trenches are useful when a continuous exposure along a given line or section is desired. In general they serve the same purpose as the pit but have the added advantage of disclosing the continuity or limits of the formations or deposits in question and any vertical faults in the rock structured. The field work consists of excavating an open trench from the top to the bottom of the slope to reach representative undisturbed material. Either a single slot trench down the face of the slope or a series of short trenches spaced at appropriate intervals along the slope may be excavated. Depending on the extent of the investigation required, use may be made of picks and shovels; bulldozers, ditching machines, back hoes or dragline. 

 

Exploration by Borings:-

When the depth of exploration is larger borings are used for exploration .

Methods of Borings (As per IS 1892:1979)

Auger boring- these are suitable for advancing holes up to a depth of 3 to 6m in soft soils

Wash boring- Used for advancing hole in the ground. This method is slow in stiff soils and coarse grained soils.

Rotary drilling- Can be used in clay sand and rocks.

Percussion drilling- used for drilling holes in rocks boulders and other hard strata

Core drilling- used for drilling holes in rock and for obtaining rock cores( for identification and tests)

Exploration by Borings and Drilling

Hand Auger Borings - Auger boring is the most common, economical and rapid method for relatively shallow exploration of fine - grained materials above the water - table. Hand augers become awkward and cumbersome beyond a depth of approximately 6 m. If the work is done carefully, the layers of different soils may be accurately located, identified classified and suitable distributed samples obtained.

 

Indirect Methods

These methods include various sounding and geophysical methods, indirectly by measuring in-situ a tool/instrument behavior during interaction with soil/rock and inference of material properties. eg. SPT, cone penetrometer  etc.
Choice of method depends on budget, sampling requirements, extent of investigation, and often site conditions.

VANE SHEAR TEST

Vane shear test (VST)- to determine shear strength of cohesive soil in its natural condition.( Is 4434:- 1978)The vane shear test is most appropriate for the determination of the shear strength of saturated clays, especially of the ‘soft’ to ‘medium’ consistency. 

The test is especially appropriate for determining the shear strength of sensitive soils which are highly susceptible to sampling disturbances.

The vane shear test consists of pushing a four-bladed vane in the soil and rotating it till a cylindrical surface in the soil fails by shear. The torque required to cause this failure is measured and this torque is converted to a unit shearing resistance of the cylindrical surface

 

Standard Penetration Test (SPT)- to determine N-value (IS 2131-1981)

IS 2131 :1981 (Reaffirmed 1987): Indian standard – Method for standard Penetration test for soils. SPT is widely used to determine the parameters of the soil in situ . The test consists of driving a split spoon into the soil through a borehole at the desired depth . This test was developed in 1920 Consist of 3 parts-

  • Driving shoe at bottom- 75mm long.
  • Steel tube, split longitudinally into 2 halves-450mm long.
  • Coupling at the top-150mm long.

The split spoon sampler is driven into the soil a distance of 450 mm at the bottom of the boring 

A hammer of 63.5 kg wt with a free fall of 760 mm is used to drive the sampler .

The no. of blows for a penetration of last 300 mm is designated as the “ Standard Penetration Value” or “Number” N

 

 

Structure Minimum No of Bore Holes
Check dams At abutment points and at 20 m intervals in
river course (minimum one number in river course).
Regulators Borehole should be taken at all pier points and
abutments. (Usually the centre to centre distance
between the pier is standardized to 14m
Side protection Works If these works are necessary, bore holes should be taken on the banks at the upstream and downstream of the structure at
30 m intervals along the required length.
Cut off walls. At positions of cut off walls , for designing Apron.

 

If the Site Engineer in charge feels that there is a necessity of closer bore holes then he should execute as per site conditions

 

Development Test Spacing Approximate Depth of Investigation
Dams 25 m to 50 m 2 x height of dam, 5 m below toe or of slope. 3 m into bedrock below toe whichever is greater. Extend into zone of low permeability.
Canals 100 m to 200 m 3 m minimum below invert level or to a zone of low permeability
Culverts
<20 m width
20 – 40 m
1 Bore hole One at each end
One at each end and 1 at
middle with maximum spacing of
20 m between bore holes
2 B – 4B but below base of compressible layer

 

SUB SOIL EXPLORATION REPORT

 

The following details should be attached to the report:

 

1. Latitude and longitude of location

2. Site location map

3. A plan view of the location of the borings with distance between them with respect to the proposed structure

4. Boring logs

5. Laboratory test results

6. SBC and N value of each layer 

7. For rocky strata, the RQD value should also be included

8. For rocky strata, the RQD value should also be included

9. Report should be authenticated by field officers.

 

BENCHMARK

LOCATION AND NUMBER OF B.M

 

PLATE LOAD TEST

 

S.No. Particulars Standard/
permanent B.M
Location &No.
Ordinary or Temporary B.M.
Location & No.
1. Major Dam &
Medium
One on either bank along the alignment Dam alignment excluding river
portion @10 chains located D/s at
a distant of five times the head of
the dam away from the C/L of the
dam.
One on Waste weir at a distance of
2 chains from the mid pointed of the
C/L of the alignment.
Spill channel & approach channel
alignment one @ every 10 chains.
2. Minor Dam One on one bank Same as for Sl. No. 1above
3 Canal alignment At every 5 km
along the
alignment, on the canal boundary line
At every one km along the
alignment, on the boundary line
excluding standard B.M.S.

INVESTIGATION-IS CODES

IS 2131-1981 Method for standard Penetration test for Soils
IS 7720-1991 Criteria for investigation planning and layout for barrages and weirs
IS 1892-1979 Code of Practice for subsurface investigation for foundations
IS 11385-2008 Sub surface exploration for canals and cross drainage works
IS 4453 :2009 Code of practice for subsoil exploration by pits trenches etc
Is 4434:- 1978 Vane shear test (VST)- to determine shear strength of cohesive soil in its natural condition.
IS 6955-1973 Bore Hole spacing guidelines for Earth and rock fill dams
IS 11385,1985 Bore Hole spacing guidelines for canals and cross drainage works
IS 2720
(Part 2)1973
Determination of water content (second revision)
IS 2720
(Part 5)1985
Determination of liquid and plastic limit (second revision
IS 6403-1981 Code of practice for determination of bearing capacity of shallow foundations.
IS 1498:1970 Classification and identification of soils for general engineering purposes (first revision
IS 2720
(Part 1)1983
Preparation of dry soil samples for various tests (second revision)